Layout drawings were created to optimize the geometry of the radial stacker based on the existing topography and maximize coke storage. Material requisitions were issued to vendors for the design and supply of the straddle carrier and radial stacker. The existing ramp was removed and the area around it reworked to provide a stable foundation for the stacker conveyor and straddle carrier. Power for the conveyor was supplied from a nearby MCC.
Vendor drawings were reviewed and incorporated in the design. Civil and mechanical construction drawings were issued to the Client, who created construction work packages to execute the work. An electrical construction work package was also created. Rally provided construction and scheduling support.